Tracker

Louisiana Data Center Tracker

Every major AI and cloud data center project announced in Louisiana, with investment, power, water and jobs as reported. Updated as of Oct. 6, 2026.

How does Louisiana compare? See the Gulf South Data Center Tracker for Mississippi and Alabama projects and deal terms side by side.

Why track power and water? Large data centers can use as much electricity as a city, and some cooling systems use a lot of water. Who supplies the power, and who pays for new plants and lines, is often the biggest public question about a project.
DeveloperParishInvestmentCapacityJobsPowerWaterStatusSources
Meta
Hyperion
Richland
Northeast Louisiana
More than $50 billion5 GW of IT capacity; nearly 10M sq ft1,000 operating; 7,500 construction at peakEntergy Louisiana (7 gas plants, 3 batteries and transmission pending at the PSC, Docket U-37882)Not specified in LED releaseUnder construction; power plan before the PSCSource · Our story
Amazon
Three campuses incl. Resilient Technology Park
Caddo and Bossier
Northwest Louisiana
$18 billion totalNot specified750 direct; 1,784 indirect; up to 2,250 constructionSWEPCO; Amazon funds grid upgradesAir cooling most of the year; water above about 85 F (under 13% of the year); up to $400M for public water infrastructurePlanned / expandingSource
Hut 8
River Bend campus
West Feliciana
Capital Region
$10 billion (WAFB, 2026) or $12 billion (WBRZ, 2026)245 MW leased to Fluidstack; right of first offer on up to 1,000 MW more; 330 MW Entergy utility capacity75+ direct (Hut 8) to 175+ permanent (parish president); about 1,000 to 1,500 constructionEntergy LouisianaClosed-loop cooling; water for restrooms trucked inUnder construction; first data hall targeted Q2 2027Source · Our story
Applied Digital
Delta Forge 1
Rapides (Boyce)
Central Louisiana
$3.6 billion300 MW critical IT load on about 300 acres200 direct; 218 indirect; 1,000+ construction at peakClecoClosed-loop, waterless coolingSite work began 2026-01; initial operations expected mid-2027Source

How to read this map

Know of a project we missed? Tell us and include a source.