Louisiana Data Center Tracker
Every major AI and cloud data center project announced in Louisiana, with investment, power, water and jobs as reported. Updated as of Oct. 6, 2026.
How does Louisiana compare? See the Gulf South Data Center Tracker for Mississippi and Alabama projects and deal terms side by side.
Why track power and water? Large data centers can use as much electricity as a city, and some cooling systems use a lot of water. Who supplies the power, and who pays for new plants and lines, is often the biggest public question about a project.
| Developer | Parish | Investment | Capacity | Jobs | Power | Water | Status | Sources |
|---|---|---|---|---|---|---|---|---|
| Meta Hyperion | Richland Northeast Louisiana | More than $50 billion | 5 GW of IT capacity; nearly 10M sq ft | 1,000 operating; 7,500 construction at peak | Entergy Louisiana (7 gas plants, 3 batteries and transmission pending at the PSC, Docket U-37882) | Not specified in LED release | Under construction; power plan before the PSC | Source · Our story |
| Amazon Three campuses incl. Resilient Technology Park | Caddo and Bossier Northwest Louisiana | $18 billion total | Not specified | 750 direct; 1,784 indirect; up to 2,250 construction | SWEPCO; Amazon funds grid upgrades | Air cooling most of the year; water above about 85 F (under 13% of the year); up to $400M for public water infrastructure | Planned / expanding | Source |
| Hut 8 River Bend campus | West Feliciana Capital Region | $10 billion (WAFB, 2026) or $12 billion (WBRZ, 2026) | 245 MW leased to Fluidstack; right of first offer on up to 1,000 MW more; 330 MW Entergy utility capacity | 75+ direct (Hut 8) to 175+ permanent (parish president); about 1,000 to 1,500 construction | Entergy Louisiana | Closed-loop cooling; water for restrooms trucked in | Under construction; first data hall targeted Q2 2027 | Source · Our story |
| Applied Digital Delta Forge 1 | Rapides (Boyce) Central Louisiana | $3.6 billion | 300 MW critical IT load on about 300 acres | 200 direct; 218 indirect; 1,000+ construction at peak | Cleco | Closed-loop, waterless cooling | Site work began 2026-01; initial operations expected mid-2027 | Source |
How to read this map
- Figures are as reported by the cited source; where sources disagree, we show both.
- Job counts mix direct, indirect and construction estimates. These are projections, not hiring records.
- SpaceX's Starbase Louisiana is a launch site, not a data center, and is covered in our Space section.
Know of a project we missed? Tell us and include a source.