Around the South

Gulf South Data Center Tracker

Louisiana and its neighbors: every data center project of $1 billion or more announced in Louisiana, Mississippi and Alabama, with the deal terms side by side. Updated as of Oct. 6, 2026.

What we mean by the Gulf South. For this tracker, the Gulf South is Louisiana, Mississippi and Alabama. Texas and Georgia are big data center markets, but they're large enough to need trackers of their own, and Georgia isn't on the Gulf.

The column to watch is deal terms: the tax breaks, payments and power arrangements each state and community agreed to. Read our comparison: How Louisiana's data center deals compare with its neighbors'.

DeveloperStateInvestmentCapacityJobsPowerDeal termsSource
Louisiana
4 projects: Meta, Amazon, Hut 8, Applied Digital
StatewideMeta's $50B+ Hyperion campus, Amazon's $18B across three northwest campuses, Hut 8's River Bend campus and Applied Digital's $3.6B Delta Forge 1. See every Louisiana project in detail.Louisiana tracker
xAI
MACROHARDRR (Colossus expansion)
Mississippi
Southaven, DeSoto County
$20+ billionBrings xAI's Colossus training compute to about 2 GW (company claim)Hundreds of permanent jobsAdjacent power plant acquired by xAISales and use tax exemption on computing equipment and software; fee-in-lieu agreements with Southaven and DeSoto County
Mississippi Today later described a $6 billion Southaven plan; figures differ by source.
Source
2026-01-08
Amazon (AWS)
Two data centers
Mississippi
Ridgeland, Madison County
$12 billionNot specifiedPart of 2,000 jobs across Amazon's four Mississippi facilitiesEntergy MississippiBuilds on Mississippi's 2024 Amazon package ($44M in state spending and tax breaks); Entergy Mississippi may build power infrastructure without prior PSC approval under 2024 law
Ridgeland site moving to recycled water by 2027.
Source
2026-04-09
Amazon (AWS)
Original Mississippi campuses
Mississippi
Madison County area
$10 billionNot specifiedPart of 2,000 jobs across four facilitiesEntergy Mississippi$44M state package (2024), a $215M loan and tax breaks, per Mississippi TodaySource
2024
Amazon (AWS)
Warren County data center
Mississippi
Near the Port of Vicksburg, Warren County
$3 billionNot specifiedAt least 200 full-timeNot specifiedCovered by existing 2024 legislation; no additional state funds, per Mississippi TodaySource
2025-11-20
Compass Datacenters
Eight-building campus
Mississippi
Meridian, Lauderdale County
$10 billion (incl. tenant IT equipment)About 500 MWThousands of direct and indirect jobs (state claim)Mississippi Power10-year state income and franchise tax exemptions; sales and use tax exemption; MDA site preparation help; $4M county site grant
Eight-year build-out.
Source
2025-01-09
AVAIO Digital
AVAIO Digital Taurus
Mississippi
Brandon, Rankin County
$6 billionNot specifiedAt least 60 directEntergy MississippiData Center Enterprises tax exemption; Site Development Grant Program help
Water-efficient cooling and rainwater recapture planned; completion targeted first half of 2027.
Source
2025-08
Applied Digital
Delta Forge 2
Alabama
Near Brookwood, Tuscaloosa County
$3.2 billion210 MW100 permanent; about 1,000 constructionNot specified$270M in community benefit payments to the Tuscaloosa County Economic Development Authority over 20 years
Operations expected 2028; end user an unnamed hyperscaler.
Source
2026-09-25
Google
Jackson County campus expansion
Alabama
Former Widows Creek coal plant site, Jackson County
$1.5 billion (2026 to 2027)Not specifiedHundreds of full-time jobs; about 1,800 construction for the expansionTVA; Google says it funds 100% of its own power and infrastructure costs30-year tax abatement, per Business Alabama
Operating since 2019.
Source
2026-06-15
Meta
Montgomery data center
Alabama
Montgomery
$1.5 billion1.3M+ sq ft at completion100+ permanent; about 1,500 construction at peakNot specifiedNot specified in the announcementSource
2024 ($800M); expanded 2025

How to read this tracker

Know of a project we missed? Tell us and include a source.