Here is the question at the center of this week's hearing: when one customer needs more electricity than an entire city, who should pay for the power plants that serve it, and how sure should regulators be that the customer will stick around?

That customer is Meta, the parent company of Facebook and Instagram. Its Hyperion data center in Richland Parish is projected to use more power than all of New Orleans, WAFB reported. Entergy Louisiana wants permission to build the generation and transmission to serve it. Starting Oct. 7, the Louisiana Public Service Commission will hear the evidence.

Quick definitions. The Louisiana Public Service Commission (LPSC) is the five-member elected board that regulates investor-owned utilities like Entergy, including what they build and what they charge. A docket is the case file for one request; this one is U-37882. An evidentiary hearing works like a trial: witnesses testify and get cross-examined in front of an administrative law judge. An intervenor is an outside group the commission allows to participate as a party.

What happens on Oct. 7

A three-day evidentiary hearing is expected to open Oct. 7, according to The Center Square's reporting, republished by the American Press on Sept. 30. The hearing covers whether Entergy's construction plan is necessary, how costs get split between Meta and everyone else, how the electricity demand was calculated, how the system is designed, and what protections exist for other ratepayers.

The commission itself does not vote at the hearing. WAFB reported in August that the commission was scheduled to vote on Entergy's generator plan in December, and The Center Square has reported a target date of Dec. 16.

What Entergy is asking for

Entergy calls the request Project Evest. As of Sept. 30, it includes, according to 10/12 Industry Report and The Center Square:

  • Seven combined-cycle natural gas units. Four would sit near the data center in Richland Parish and three near the Big Cajun plant in Pointe Coupee Parish. A combined-cycle unit burns gas in a turbine, then captures the waste heat to make steam for a second generator.
  • Three battery-storage projects.
  • A new interconnection substation.
  • More than 250 miles of 500-kilovolt and 230-kilovolt transmission lines.

This is a second round. Regulators approved an earlier package of three gas plants for the original Meta project in August 2025, and Entergy CEO Phillip May has said the new infrastructure is required "beyond those approved in August 2025," according to The Center Square.

The reason for the second round is scale. On July 13, Louisiana Economic Development announced that Meta had raised its Richland Parish commitment to more than $50 billion, with nearly 10 million square feet and 5 gigawatts of IT capacity. The state projects 7,500 construction jobs at peak and 1,000 operating jobs.

The argument for the plan

Entergy's case is that the deal lowers costs for other customers because Meta's long-term contract helps pay for shared infrastructure. LED's July announcement said the Entergy agreement is expected to produce more than $2 billion in customer savings. The Louisiana Illuminator reported Entergy's projection as $2.6 billion in savings over two decades, as part of roughly $15 billion in power infrastructure.

Entergy has also said the new transmission matters beyond Meta. At a public meeting about a proposed 500-kilovolt line from Richland Parish toward Avoyelles Parish, Entergy vice president Larry Hand said, "If we don't have this line, we will not be able to service generators around the state for maintenance or transmission lines," KALB reported on Oct. 3.

The argument against it, or for more conditions

The main intervenors include the Alliance for Affordable Energy, the Union of Concerned Scientists and the Sierra Club, along with industrial customers and consumer advocates. Their concern is risk. If Meta's demand comes in lower than forecast, or if the company leaves when its contract ends, other customers could be left paying for plants built for one user.

The Union of Concerned Scientists told the Illuminator that Entergy's analysis "leaves little to no room for deviating from expectations." Hand acknowledged the contract question directly at the Oct. 1 meeting: "It's a 20-year contract with Meta for this current project [and] what happens after 20 years is they either renew or they don't."

Landowners are a newer front. KALB reported that a coalition led by LaSalle Parish rancher Dustin McAnn opposes the West Fork Creek to Boeuf 500-kilovolt line, citing surveyors on private land and the risk of expropriation, which is the legal process for taking private property for public use with compensation.

The records fight, explained

A lot of the public debate has been about what the public can't see. Here is the timeline, as of Oct. 4:

DateWhat happened
June 30, 2026A subpoena is issued to Meta's subsidiary, Evest LLC, at the request of the Alliance for Affordable Energy and the Union of Concerned Scientists, seeking investment projections, job estimates and electricity load calculations. (WWNO)
July 10Administrative Law Judge Melanie Verzwyvelt grants the subpoena in part. (WWNO)
July 31The judge declines to reconsider and refers the dispute to the full commission. (WWNO)
Aug. 12The commission votes to vacate the subpoena. Commissioner Davante Lewis casts the only vote against. (WAFB)
Sept. 4Entergy and the two nonprofits reach an agreement letting seven designated representatives review "attorney's eyes only" materials at Entergy's New Orleans offices, with no notes or copies allowed. (Louisiana Record)
Sept. 17The commission issues its written order, U-37882-A, formally reversing the judge and vacating the subpoena. The order records a 3-1 vote: Vice Chairman Coussan moved, Chairman Skrmetta seconded, Commissioner Francis concurred, Lewis opposed and Commissioner Campbell was absent. (Order copy)

The practical result: intervenors' lawyers and experts can examine some of Meta's numbers under strict limits, but the public cannot. That is common in utility cases involving trade secrets. What makes this case different is its size.

Meta, notably, is not listed among the hearing's witnesses, 10/12 Industry Report noted.

What the data does and doesn't tell us

A few honest caveats before you form a view:

  • The savings figures are projections from Entergy, not audited results. They depend on Meta's actual demand and on gas prices over 20 years.
  • The risk figures are also arguments. Intervenors have said some of the units may not be needed. Counsel for the advocates said "it may well be that only two are justified," WWNO reported. That is a position, not a finding.
  • Nobody outside the confidentiality agreement has seen the load forecast that drives the whole request. Neither side's public claims can be fully checked until the commission rules and explains why.

How to follow along

Filings, testimony and orders in Docket U-37882 are posted through the LPSC's electronic docket system. Commission votes happen at monthly Business and Executive sessions. We will post updates after each hearing day.

Verify it yourself

If you live in Entergy Louisiana's territory, what would you want commissioners to ask Meta and Entergy before they vote? Tell us and we'll bring the best questions into our hearing coverage. Send us a note.

Sources

  1. American Press / The Center Square: Two hearings stand between Meta and its power buildout (Sept. 30, 2026)
  2. 10/12 Industry Report: PSC to consider Entergy Louisiana's infrastructure expansion plans in support of Meta (Sept. 30, 2026)
  3. Louisiana Economic Development: Meta commits more than $50 billion (July 13, 2026) (Primary source)
  4. Louisiana Illuminator: As Meta data center expands, advocates push harder for transparency (Aug. 5, 2026)
  5. WWNO: Judge sends Meta subpoena fight to full Public Service Commission (July 31, 2026)
  6. WAFB: Regulators allow Meta to keep data center records secret (Aug. 12, 2026)
  7. Louisiana Record: Agreement ends La. fight over access to data center info (Sept. 4, 2026)
  8. KALB: Louisiana landowners oppose transmission line meant to support Meta's data center (Oct. 3, 2026)
  9. LPSC Order U-37882-A (Sept. 17, 2026), copy hosted by a third party (Third-party copy; confirm against the LPSC docket)
  10. S&P Global Commodity Insights: Louisiana regulators approve new Entergy infrastructure for Meta data center (Aug. 2025) (Headline only reviewed)
  11. Louisiana Public Service Commission (Primary source for docket U-37882)