Quick answer: In Louisiana, an electric utility can ask a court to take a right of way across private land for power lines, a process called expropriation. It has to show a public purpose and necessity, make a good-faith offer first and pay the owner for the full extent of the loss. An Ouachita Parish family is now challenging Entergy Louisiana's right to do that for lines tied to Meta's data center.

Harvey Parnell Perry and John W. Perry Jr. didn't wait for Entergy Louisiana to sue them. After the utility sent them a notice in September 2025 and a formal offer in October 2025 for a right of way across their Ouachita Parish land, the Perrys went to court first, asking a judge to declare that Entergy can't take it, the Ouachita Citizen reported on Nov. 4.

The land is on the route of Entergy's Car Gas Road to Smalling transmission project, which the utility's filings describe as part of a larger build serving Meta's Hyperion campus in Richland Parish and other customers.

Quick definitions. Expropriation is Louisiana's term for eminent domain: the government, or a company the law authorizes, taking private property for public use with payment. A servitude is a right to use someone else's land for a set purpose, like stringing power lines, while the owner keeps the title. A right of way is the strip of land a servitude covers.

The case so far

  • What Entergy wants. A servitude, not ownership. Its notice to the Perrys covered about 139 acres, according to the Ouachita Citizen.
  • The family's argument. The Perrys say the lines would mainly serve Meta, not the public, so Entergy lacks the public purpose and necessity the law requires. They also say Entergy's later group petition leaves out related land and a second line across their property.
  • Entergy's argument. In court filings, Entergy says its existing system "currently cannot serve" Meta's data center, that the new lines will also support growth and other customers, and that the Perrys sued too early, before the legal steps for expropriation had played out.
  • Others named. Entergy's own petition names several other landowners along the route, including residents of other states.
  • Status. Neither side appeared at an Oct. 27 hearing, and no new date has been set, the paper reported.

The bigger build

Entergy's plan to serve Meta includes new generation and new high-voltage lines across northeast and central Louisiana. Its fact sheet for one segment describes two new 500-kilovolt lines of about 25 miles each through Ouachita, Morehouse and Richland parishes, with construction from summer 2026 through 2027, according to Entergy Louisiana. That sheet doesn't name the Perrys' line, so we can't confirm its voltage.

Farther south, landowners along a proposed line from Richland Parish toward central Louisiana have formed a coalition. Entergy vice president Larry Hand told KALB in October that at least 70% of landowners on that route had signed survey agreements and that Entergy is required to negotiate in good faith. On Nov. 9, that coalition and two other groups sued the Public Service Commission over the fast-track rules used for Entergy's Meta request, KRVS reported.

How expropriation works in Louisiana

1. Who can do it

State law, R.S. 19:2, lets an electric public utility expropriate for lines that are in a grid operator's expansion plan or are needed for reliability or to connect a generator. The facilities must mainly serve customers in Louisiana.

2. What has to happen before a lawsuit

Under R.S. 19:2.2, the utility must try in good faith to reach a deal. It has to share its appraisal, offer at least the lowest appraised value, send a notice of the owner's rights and, at least 30 days before filing, send a certified letter explaining the legal basis, the route, the compensation offered and a surveyor's plat. Skipping steps can get a case thrown out as premature, as happened to Entergy in a separate 2026 appeals case, Entergy Louisiana v. Mudd Family Partnership. (We haven't confirmed whether that case involved Meta-related lines.)

3. The constitutional limits

Louisiana's Constitution, Article I, Section 4, allows taking property only for a public purpose and with just compensation. After the U.S. Supreme Court's 2005 Kelo decision, Louisiana voters tightened it in 2006: property can't be taken "for predominant use by any private person or entity," and economic development alone isn't a public purpose. The amendment counts property dedicated to public utilities as a public purpose. Whether a line built largely for one customer crosses into "predominant private use" is the kind of question the Perry case raises. We found no court ruling on it for these lines.

4. Getting paid

Owners are owed compensation "to the full extent of his loss," and either side can ask for a jury on the amount. Under R.S. 19:8, a court may award the landowner reasonable attorney fees if the final award is higher than the utility's best offer. With a servitude, payment covers the right of way plus any loss in value to the rest of the property.

What changed in 2026

Lawmakers passed limits on expropriation by foreign adversaries (Act 277, approved by voters Nov. 3 as a constitutional amendment) and asked the Louisiana State Law Institute to study the state's expropriation authority (HCR 61). A broader landowner bill, HB 841, which would have made private takers pay court costs, didn't pass. None of the 2026 changes targeted utility lines or data centers.

If Entergy contacts you about your land

  • Keep every letter. The dates matter, because the law sets a sequence of notices before a suit can be filed.
  • Ask for the appraisals and the surveyor's plat. The law requires the utility to share them.
  • Talk to a lawyer who handles expropriation before signing. Compensation and the terms of a servitude are negotiable.

This is general information, not legal advice.

Verify it yourself

Has a utility contacted you about a right of way for new lines? Tell us how it went. Send us a note.

Sources

  1. Ouachita Citizen: Local family fights Entergy in court over land running power to Meta AI data center (Nov. 4, 2026)
  2. Entergy Louisiana: NELA 500kV transmission lines fact sheet (primary source)
  3. KALB: Louisiana landowners oppose transmission line meant to support Meta's data center (Oct. 3, 2026)
  4. KRVS: Entergy wants their land for Meta's power lines. They're suing the regulators approving them (Nov. 9, 2026)
  5. Louisiana Legislature: R.S. 19:2 (primary source)
  6. Louisiana Legislature: R.S. 19:2.2 (primary source)
  7. Louisiana Legislature: R.S. 19:8 (primary source)
  8. Louisiana Constitution: Article I, Section 4 (primary source)
  9. Leagle: Entergy Louisiana v. Mudd Family Partnership (La. App. 3 Cir., July 15, 2026)
  10. WAFB: Louisiana voters pass constitutional amendments (Nov. 4, 2026)