When Hut 8 first brought Phase II of its River Bend campus to West Feliciana's Planning and Zoning Commission in October, the plan put a data center building less than a mile from homes in Star Hill, near La. 10 and U.S. 61. Neighbors came to that Oct. 5 meeting with questions about heavy-industrial zoning, land Hut 8 might not develop for years and noise. At the commission's next meeting, on Nov. 2, Phase II was put off again, and Hut 8 didn't attend, The Advocate reported.
"Hut 8 is taking additional time to refine the design of Phase II," Hailey Miller, the company's senior director of public affairs, told the paper. She said updated applications will be filed in December for consideration in January.
What Phase II covers
- About 180 acres.
- Two buildings of about 568,000 square feet each, plus substations and a switchyard.
- A request to rezone land, which Hut 8 now plans to scale back so it no longer needs to rezone land along La. 10, according to parish development services director Gary Mego.
- At least one building will likely move closer to the Phase I site on La. 964, Mego said.
The Advocate's report doesn't give a power figure for Phase II.
What neighbors raised
- Zoning next to homes. Residents objected to heavy-industrial zoning next to subdivisions.
- Land banked for later. They asked why land Hut 8 wouldn't build on right away needed rezoning, saying it could let the campus creep closer over time.
- Noise. Hut 8's noise study was measured more than two miles from homes, so it couldn't answer questions about the closer site.
What happens next
| Date | Step |
|---|---|
| Dec. 1 | Deadline for Hut 8 to resubmit its site plan and rezoning applications, so hearing notices can run a month ahead |
| Jan. 4, 2027 | Planning and Zoning Commission public hearing |
| After the hearing | The commission's recommendation goes to the West Feliciana Parish Council for a decision |
Phase I keeps going
Phase I sits on more than 600 acres Hut 8 owns. The company signed a 15-year lease with Fluidstack for 245 megawatts of computing capacity, with Google backstopping the lease payments, and Entergy Louisiana has secured an initial 330 megawatts of utility capacity, according to Hut 8's December 2025 announcement. Vertical construction was underway by August, and the company is targeting its first data hall for the second quarter of 2027. In October, Hut 8's Matias DuRei pointed to about $16 million in water system improvements and work with the state transportation department on the U.S. 61 and La. 964 intersection.
West Feliciana is also the parish where the president says he negotiated without a nondisclosure agreement. (See our story on that deal.) Phase II is now going through the same public zoning process as any other large project, with a hearing on the calendar and a council vote at the end.
How to weigh in
The Jan. 4 hearing is open to the public. Agendas and applications are posted by West Feliciana Parish government ahead of each commission meeting.